UPSC Mains 2014 · GS III · Q15 · 12.5 marks · 200 words

Environmental Impact Assessment studies are increasingly undertaken before a project is cleared by the Government. Discuss the environmental impacts of coal-fired thermal plants located at coal pitheads.

हिन्दी में

सरकार द्वारा किसी परियोजना को अनुमति देने से पूर्व, अधिकाधिक पर्यावरणीय प्रभाव आकलन अध्ययन किए जा रहे हैं। कोयला गर्त-शिखरों (पिटहेड्स) पर अवस्थित कोयला-अग्नित तापीय संयंत्रों के पर्यावरणीय प्रभावों पर चर्चा कीजिए।

How a topper answered the closest question

Toppers wrote this one in a test series: “What do you mean by Environmental Impact Assessment? Discuss the major reasons that have limited the success of EIA. Suggest measures that can be taken to make EIA an effective tool.”

Priyansha GargAIR 31 · CSE 2022 · 317 wordsTheir whole copy

Opening · a definition

Environment Impact Assessment is a tool to address and find the impact of any project on the Environment and thus understand its viability.

Body · points

Environment Impact Assessment is a tool to address and find the impact of any project on the Environment and thus understand its viability.

Steps of EIA

Diagram
project -> screening -> EIA required -> Yes -> Scoping -> Assessing -> Analysis -> Monitoring -> it passed -> Regulation -> No

Reasons for limited success

(1) Lack of transparency in assessment process leading to licence raj.

(2) Low deterrence due to non-enforcement of penalties.

(3) Lack of proper classification into white, green, red, orange industries.

(4) Poor judicial system to held accountability.

(5) Lack of people's participation and their ignorance leads to surpassing of rules.

Measures to make EIA effective

(1) Using ICT and digital portals to carry out assessment and reduce licence raj as done in 48 hours report for MSME.

(2) Carrying out social audit on regular basis to improve regulations and adherence to EIA rules.

(3) Designating a separate board to address EIA related issue.

(4) Fast-track courts for quick enforcement and remedy.

(5) Effective guidelines, proper classification and easy compliance methods using good governance.

Also a step can be taken to address combined Environment and Social Impact Assessment to ensure communities are not harmed in setting of industrial projects.

tourism, health and poor management that leads to floods and other disasters.

Plastic waste management Rules, 2016 & other measures

(1) It extends the responsibility to the producer to collect back plastic (Extended producer responsibility).

(2) India has committed to reduce plastic waste by banning 'Single use plastics' -> 'BEAT Plastic'.

(3) Minimum thickness of plastic increased to 50 microns to make it costly. This will reduce free giving of plastic bags.

(4) Engaging with the informal sector - rag pickers to make waste collection effective and economical.

(5) Segregation at source directives for individuals.

(6) Nudge towards Circular Economy. However there are many challenges that India face like

  • job loss
  • increasing cost of production
  • status quo by individuals etc

In beating plastic waste we need to generate awareness and responsibility to ensure

Diagram
A central node '6RS' with outward arrows connecting to 'Remanufacture', 'Refurbish', 'Reduce', 'Reuse', 'Recycle', 'Redesign'.

to beat plastic.

Close

In beating plastic waste we need to generate awareness and responsibility to ensure to beat plastic.

How toppers approach this question, and more on its topic: open the question.

Toppers’ answers to other close questions

Source: UPSC, Civil Services (Main) Examination 2014, General Studies Paper III, Q15. The paper on upsc.gov.in. Themes and links to toppers’ answers are by UPSC Grade, not by UPSC.