Scheme

PLI Scheme: National Programme on Advanced Chemistry Cell (ACC) Battery Storage

GS3 Industry and energy storagePrelims and Mains

In the news since 6 February 2026 · last on 27 March 2026

Why in news
On 27 March 2026, the Minister of State for Heavy Industries told the Rajya Sabha that 40 GWh of the 50 GWh PLI ACC capacity is awarded to four firms, and that domestic demand is still met mostly by imports.
What it is
The National Programme on Advanced Chemistry Cell (ACC) Battery Storage is a Production Linked Incentive scheme run by the Ministry of Heavy Industries. It gives incentives to firms that set up large-scale ACC manufacturing in India. ACCs are new-generation devices that store electrical energy as electrochemical or chemical energy and convert it back to electricity when needed.
Approval and outlay
The scheme was approved in May 2021 with a total outlay of ₹18,100 crore.
Target capacity
The scheme aims to build 50 GWh of domestic ACC manufacturing capacity.
Capacity awarded
Of the 50 GWh, 40 GWh has been awarded to four beneficiary firms.
Aim
The scheme seeks to cut dependence on imported ACCs and build a globally competitive manufacturing ecosystem.
Technology
Beneficiary firms report using in-house developed ACC technology.
Administering ministry
The scheme is administered by the Ministry of Heavy Industries.
Implementation challenges
Firms face limited technology, a skilled manpower gap, dependence on imported critical equipment and no upstream components such as CAM, AAM and electrolyte.
National Critical Mineral Mission
Run by the Ministry of Mines, approved on 29 Jan 2025, to secure the critical mineral value chain from exploration to recovery from end-of-life products.
Outlay and capacity
Approved in May 2021 with an outlay of ₹18,100 crore to build 50 GWh of domestic ACC capacity.
Incentive basis
Incentive depends on the subsidy per kWh quoted by the firm and the percentage of value addition achieved on actual sales.
Value addition targets
At least 25% value addition within 2 years at Mother Unit level, rising to 60% within 5 years of the appointed date.
Technology neutrality
The scheme is technology agnostic, and superior technologies get higher incentives. R&D spending counts towards investment criteria.

Don’t confuse with PLI ACC vs FAME / PM E-DRIVE: PLI ACC subsidises battery cell manufacturing. FAME and PM E-DRIVE support electric vehicle demand and adoption.

Don’t confuse with PLI ACC vs PLI-Auto: PLI ACC supports making battery cells; PLI-Auto supports automobiles and auto components. Both are run by the Ministry of Heavy Industries.

Don’t confuse with PM E-DRIVE vs PLI ACC: PM E-DRIVE promotes EV adoption through demand-side support; PLI ACC is a supply-side manufacturing incentive.

Don’t confuse with PLI ACC vs FAME/PM E-DRIVE: PLI ACC subsidises domestic battery cell manufacturing; FAME and PM E-DRIVE support demand for electric vehicles.

Schemes: 52 Prelims questions since 2013, 10 in Prelims 2026 alone. They test features, the period and who funds it. In Mains, 33 news-triggered questions, mostly GS3.

Test yourself

Worth revising until Prelims 2027: most news questions come within two years of the event.

Each time it was in the news

  1. 27 March 2026

    On 27 March 2026, the Minister of State for Heavy Industries told the Rajya Sabha that 40 GWh of the 50 GWh PLI ACC capacity is awarded to four firms, and that domestic demand is still met mostly by imports.

  2. 13 February 2026

    On 13 Feb 2026, the Minister of State for Heavy Industries told the Rajya Sabha that 40 GWh of the 50 GWh PLI ACC capacity is awarded, with only ₹3,237 crore invested by 31 Dec 2025.

  3. 6 February 2026

    On 6 February 2026, the Minister of State for Heavy Industries told the Rajya Sabha about the PLI ACC scheme, including Round-2 terms and Reliance's agreement for 10 GWh.