Why in news
On 10 August 2026 the Jal Shakti Ministry told Rajya Sabha the status of the 30 river-linking projects under the National Perspective Plan. Only the Ken-Betwa link has entered implementation as a priority link.
What it is
The National Perspective Plan (NPP) is the Government of India's plan for inter-basin water transfer, moving water from surplus to deficit river basins. It has a Peninsular and a Himalayan component. The National Water Development Agency (NWDA) studies and prepares reports for the links.
Number of links
30 links were identified under the NPP: 16 Peninsular and 14 Himalayan.
Implementing agency
NWDA has been given the work of river interlinking.
Environmental safeguards
An EIA is part of every FR and DPR. Ken-Betwa has an Integrated Landscape Management Plan.
Kosi-Mechi
The inter-state Kosi-Mechi link was dropped because of international dimensions. NWDA studied an intra-state version for Bihar.

Don’t confuse with Ken-Betwa vs Polavaram: Ken-Betwa is a priority NPP link implemented as a central project. Polavaram is a National Project executed by Andhra Pradesh and the Polavaram Project Authority.

Don’t confuse with Peninsular vs Himalayan component: The Peninsular component has 16 links and the Himalayan has 14. Himalayan links involve Nepal and Bhutan-side rivers in some cases.

Schemes: 52 Prelims questions since 2013, 10 in Prelims 2026 alone. They test features, the period and who funds it. In Mains, 33 news-triggered questions, mostly GS3.

Test yourself

Worth revising until Prelims 2028: most news questions come within two years of the event.

Each time it was in the news

  1. 10 August 2026

    On 10 August 2026 the Jal Shakti Ministry told Rajya Sabha the status of the 30 river-linking projects under the National Perspective Plan. Only the Ken-Betwa link has entered implementation as a priority link.