Question 7: Basic Numeracy

A certain number of men can complete a piece of work in 6k days, where k is a natural number. By what percent should the number of men be increased so that the work can be completed in 5k days?

a10%
b(50/3)%
c20%
d25%

AnswerUPSC’s answer is (c).

The work is fixed, so the number of men is inversely proportional to the number of days. Men × days is constant: M × 6k = M′ × 5k, so M′ = 6M/5 = 1.2M. That is a 20 percent increase. The value of k cancels out, so it does not matter. Remember: for the same work, if time falls from T1 to T2, men must rise by (T1 − T2)/T2, here (6 − 5)/5.

Why each option is right or wrong
  • (a) Wrong. A 10% increase gives 6k ÷ 1.1, about 5.45k days, not 5k.
  • (b) Wrong. 50/3 percent means 7/6 of the men, giving 36k/7, about 5.14k days, not 5k.
  • (c) Right. 6/5 = 1.2, so the men must rise by 20%.
  • (d) Wrong. A 25% increase gives 6k ÷ 1.25 = 4.8k days, not 5k.

Answer: UPSC’s key. Explanation: written by UPSC Grade, not by UPSC.