Roadmap for 100 GW Pumped Storage Projects (CEA)

GS3 Infrastructure - EnergyPrelims and Mains

In the news since 23 January 2026

Why in news
On 23 January 2026, at the close of the Power Ministry's Chintan Shivir at Parwanoo, Power Minister Manohar Lal released a CEA report on a roadmap to 100 GW of pumped storage by 2035–36.
What it is
The Central Electricity Authority's roadmap plans long-duration energy storage using hydro pumped storage projects (PSPs). PSPs pump water uphill when power is surplus and release it through turbines when demand is high. The roadmap assesses state-wise potential and suggests a phased capacity addition plan.
Target
The roadmap aims to commission 100 GW of pumped storage projects by 2035–36.
Storage need
The report projects storage needs of 62 GW by 2029–30 and 161 GW by 2034–35.
Driver
The need rises from non-fossil capacity growing to 500 GW by 2030 and 701 GW by 2035.
Preferred design
The report especially recommends off-stream closed-loop projects.
Publisher
The Central Electricity Authority is a statutory body under the Ministry of Power, set up under the Electricity Act, 2003.
Wider storage goal
The Shivir discussed a target of 300 GWh storage capacity by 2030.

Don’t confuse with Off-stream closed-loop vs on-stream PSP: Off-stream closed-loop projects use two reservoirs away from a river and recycle the water, so they have less impact on river flows. On-stream projects are built on a river.

Don’t confuse with GW vs GWh: GW measures power capacity (the rate of output). GWh measures stored energy. The 100 GW PSP target is capacity; the 300 GWh target is energy.

Reports and indices: 14 Prelims questions since 2013; they test who publishes a report and what it measures.

No practice question for this one; the card may still help an answer. Why: Energy storage topic is lasting and on syllabus; release gives only headline of the CEA roadmap, so too few facts for a question. Reports are 14 of 327 Prelims questions.

Worth revising until Prelims 2027: most news questions come within two years of the event.

Each time it was in the news

  1. 23 January 2026

    On 23 January 2026, at the close of the Power Ministry's Chintan Shivir at Parwanoo, Power Minister Manohar Lal released a CEA report on a roadmap to 100 GW of pumped storage by 2035–36.