Why in news
The Union Cabinet approved the CAPEX Support Scheme to Promote Critical Mineral Processing on 4 November 2026, with an outlay of ₹2,814 crore. PIB issued a backgrounder on it on 5 November 2026.
What it is
This is a central scheme that gives a capital subsidy to firms building domestic plants that refine lithium and nickel into high-purity products. It targets India's heavy import dependence on refined critical minerals. Beneficiaries are picked by competitive bidding and paid against project milestones.
Subsidy and plants
30% of eligible investment is given as subsidy for four plants: two lithium (at least 30 kt each) and two nickel (at least 50 kt each).
Caps per beneficiary
Support is capped at ₹500 crore per lithium beneficiary and ₹900 crore per nickel beneficiary.
Selection
Two stages: technical qualification, then financial bidding on the least-cost criterion, i.e. the lowest CAPEX support sought.
Governance
The apex Governing Council is chaired by the Secretary, Ministry of Mines. It makes the final selection of beneficiaries. A Techno-Financial Committee evaluates applications and a Project Management Agency supports implementation.
Commissioning timeline
The plant must be commissioned within three years of the Letter of Award, and in any case within five years. Delay beyond three years triggers tapering of the remaining support.
Support rate
Capital subsidy is 30% of eligible investment for four plants: two lithium and two nickel.
Caps
Support is capped at Rs 500 crore per lithium beneficiary and Rs 900 crore per nickel beneficiary.
Disbursal and cobalt
Incentives are paid in three milestone-linked tranches. Cobalt is expected as a by-product of nickel production.

Don’t confuse with CAPEX scheme vs NCMM recycling scheme: The CAPEX scheme (₹2,814 crore) subsidises lithium and nickel processing plants. The ₹1,500 crore recycling scheme, approved on 3 September 2025 under NCMM, promotes recovery of critical minerals from e-waste and spent batteries.

Don’t confuse with Lithium plants vs nickel plants: Lithium: at least 30 kt, cap ₹500 crore. Nickel: at least 50 kt, cap ₹900 crore.

Schemes: 52 Prelims questions since 2013, 10 in Prelims 2026 alone. They test features, the period and who funds it. In Mains, 33 news-triggered questions, mostly GS3.

Test yourself

Worth revising until Prelims 2028: most news questions come within two years of the event.

Each time it was in the news

  1. 5 November 2026

    The Union Cabinet approved the CAPEX Support Scheme to Promote Critical Mineral Processing on 4 November 2026, with an outlay of ₹2,814 crore. PIB issued a backgrounder on it on 5 November 2026.

  2. 4 November 2026

    On 4 November 2026 the Union Cabinet approved the Capex Support Scheme to Promote Critical Mineral Processing, with an outlay of Rs 2,814 crore over five years, for lithium and nickel processing.